- Get Pre-Qualified
- Choose your floor plan and lot
- Write purchase contract
- Apply for financing
- Plan Review
Sign off on blueprints
10% deposit due (Deposit will be applied toward down payment due at closing) - Personalized Color Selection
- Plot Plan applied for
- Sign off on Plot Plan (approximately 1 business week from blueprint sign-off)
- Apply for building permit (approximately 3-5 weeks after plot plan is signed)
- Finalize color Selection
- Permit issued and building begins
- Select Appliances (Upgrade Only) at Custom Distributors
- Select Flooring at Classic Carpet
- Select Lighting at Ferguson
- Pre-Closing walkthrough (A few days prior to closing)
- Closing (Approximately 180 days after permit is received)